HI,When the initial and ...
Published by MOHAMMED NAZEER, Technical lead-DY at We build group-Fisia
HI,When the initial and normalising load the RO we need to maintain total pressure drop not exceeds per PV 60 PSI.otherwise hydrolysis and damage of membrane will occur. First data of commissioning is very important to prepare history.